Each floor of each of Price Hall's wings hosts a student lounge which underwent renovation. Previously underutilized small study spaces were removed resulting in larger floor lounges, increasing the amount of community space available to students. Kitchenettes were also added to each floor.
Project design began in November 2019 when the campus brought Mach Architecture on board. Because of the accelerated schedule, the contractor was brought into the project in January to establish price, review constructability, and verify product availability and lead times, minimizing issues during construction. Construction began May 2020 and was completed in August 2020.
Design: Nov. 2019 - Mar. 2020
Construction: May 2020 - Aug. 2020
Cost of Construction: $4,900,000
Cost per Bed: $20,762 (236 beds)