Crews continue to move forward on the segment between 16th Street and 18th Street. During this past week, work continued on retaining walls, pavement removals and subgrade. Next week, crews will begin placing new subbase material and the first segments of new concrete pavement. Water main installation may also resume going west from 20th Street.  

Between 24th Street and Edgewood Road, crews are working on relocating underground private utility lines. This relocation work is in advance of 2021 roadway construction. 

As always, if you have questions or concerns, please do not hesitate to contact a member of our project team. Have a safe Independence Day weekend!