This week, crews will begin base preparations on
O Avenue at 16th Street, readying the road for new pavement. Weather permitting, pavement placement will begin toward the end of the week, and continue into the following week. Work this week will also continue on retaining walls, water services, and pavement removals and base preparation from 16th Street to 18th Street.  

In the weeks ahead, additional utility work will be underway, including water main installation going west of 20th Street, and relocation of gas utilities going west of 24th Street.  Pavement removals will also extend west to 20th Street. While this work takes place, crews will always keep at least one lane open for resident access. Please access your property from the west end of the project. 

As always, if you have questions or concerns, please do not hesitate to contact a member of the City’s project teamWe appreciate your patience during this time!