The project on O Ave continues to progress as expected. In the coming 2-3 weeks, the contractor will pave O Ave between 11th St and 13th St. Crews will also continue to work on sanitary sewer, storm sewer, and water main between 8th St and 11th St. They will continue to construct retaining walls.
As always, thank you for your patience, and if you have any questions, please do not hesitate to reach out to us.
|