City of Birmingham, MI
Old Woodward Reconstruction Project Update - 5/7/18
Coming off a busy weekend of work which resulted in the connection to the new water main system for all businesses north of Maple, contractors are underway this week (week of May 7th) targeting sewer and storm drain work as well as water main work on both the north and south ends of the project.
 
With 25 percent of the project now completed, contractors are preparing to start similar water main connection/shutdown service work for businesses along Maple within the project work zone. More details on this process will be released once they are finalized later this week. Please watch for important updates.
 
The City encourages the public to support the merchant community by visiting your favorite locations in downtown Birmingham. Remember that parking is now free in all five of the City parking structures on weekends (Saturdays and Sundays) during construction. Payment is required, however, for on-street metered parking, except on Sundays. Finally, free, two hour valet parking (then $5 for each additional hour) Monday through Saturday, 10:00 a.m.-6:00 p.m. is available at four locations near the construction zone:  
  • North Old Woodward Ave. near Willits
  • Henrietta near Maple
  • South Old Woodward near Brown
  • Hamilton Row near Ferndale
Stay Informed : Learn more about the project at www.bhamgov.org/downtowninfrastructure . Receive real time updates by email or text by  signing up for an e-notify system for the project at www.bhamgov.org/enotify .

Businesses are OPEN during construction and need your support. Enjoy free valet, Birmingham Bonus Bucks, an Art Contest  a nd more!
 