Project Spotlight Issue | June 2019
Speedy Construction for Victor Hills Project
Due to modifications needed to overcome site work challenges, construction mobilization launched on-time at the end of October 2018. Which required modifications to extensive mass grading and excessive topsoil placement. In addition to, unexpected weather challenges caused by an increase of rainfall impacting construction progress. Under knowledgeable team leadership and collaboration with stakeholders, the project overcame several obstacles to exceed all expectations and continues to readjust and accelerate construction towards completion.
Building B
As of Mid-June, Building B has completed 100% construction on walls and structural steel. Progress continues with roofing & MEP’s nearing completion, as well as 50% of site paving in the 3-week outlook projection. 
Anticipated Completion Date: August 2019
Building A
The 3-week projection outlook for Building A expects 100% completion of construction for panel erections, steel erections, and roofing. In addition to, making headway on construction of MEP and site paving activities.
Anticipated Completion Date: September 2019