WEST SIDE AERIALS
The Kualakaʻi (East Kapolei) Station is approaching 75% completion. Communication and power conduits are being installed along with on-site utilities. Walkway railings are also going up with fencing installation not far behind. Engineers plan to energize Kualaka'i soon.
The Keona'ae (UH-West Oahu) Station is nearly 85% complete with fare gates and entryway work expected soon. The Honouliuli (Ho'opili) Station is also approaching 85% completion.
Closest to completion is the H
ō'ae'ae (West Loch) Station above Farrington Highway in Waipahu. At 92% complete, crews are preparing to install entryway tile and shelter canopies atop the station. Similarly, the Pouhala (Waipahu Transit Station) is nearing completion with crews anticipating ground floor slab installation and the completion of the mauka (Moloalo Street) entrance in the coming months.
The H
ālaulani Station at Leeward Community College is approaching 85% completion with crews there ready to begin work on repairing the station's adjacent parking lot. The Waiawa Station at Pearl Highlands is 75% complete with crews prepping to install escalators and elevators in the near future.
The Kalauao Station near Pearlridge Center is more than two-thirds through its construction work. Work continues on the station's pedestrian bridge, entry stairs, escalators, and elevators. Shelter canopies are also planned for installation in the coming months.