Daniel Elementary Heating System Replacement
Design began this year with installation expected in the summer of 2020.
Grass Lake Energy Management System (DDC Controls)
Design phase began in April and scheduling begins after plans are approved.
Kent-Meridian Tennis Courts
Scheduled to be resurfaced this summer, and they will also receive an equipment storage shed.
Meeker Field
Design began in spring with the preliminary survey to be completed by June and more schedule information to follow.
Meridian Elementary Heating System Replacement
Design began this year with installation expected in the summer of 2020.
Neely O'Brien HVAC
The contractor is in the process of ordering equipment. Construction will begin in June, work is expected to be completed in August.
Northwood Fields
Weather has stopped progress on Phase I. This work will resume and Phase II will begin in the summer.
Sunrise HVAC
The contractor is in the process of ordering equipment. Construction will begin in June, work is expected to be completed in August.
New Dumpster Platforms at All Schools
This multi-year project entails replacing all wood dumpster platforms with new aluminum platforms.