Still Want More Info? 
Want to learn about the work being done by the CCTID?

Come to our next board meeting on Friday, June 8, at 9 a.m., at the Clermont County Engineer's Office.

Tell Us What You Think!
Email: 
 
Phone:
513-835-2417
 
Like us on Facebook

Follow us on Twitter

Members of the CCTID
Jeff Wright -
Chair of the CCTID and Miami Township Administrator
 
Ken Geis -
Vice-Chair of the CCTID and Union Township Administrator
 
Pat Manger, P.E., P.S. -
Secretary-Treasurer of the CCTID and Clermont County Engineer
 
Andy Kuchta -
CCTID Board Member and Director of the Clermont County Department of Community and Economic Development
 
Jeff Lykins -
CCTID Board Member and  CEO of Lykins Energy Solutions
 
John Becker -
Ex-Officio Member of the CCTID and State Representative, Ohio's 65th House District
 
Joseph Uecker -
Ex-Officio Member of the CCTID and State Senator, Ohio's 14th Senate District


Branch Hill-Guinea Widening Project Will Begin Monday, June 4
The Branch Hill-Guinea Pike widening project will add a center turn lane and paved shoulders on Branch Hill-Guinea Pike, as well as a sidewalk along the east side of the road from Bridle Path Lane to Jer-Les Drive. Drainage improvements also will be made.  

In addition to the roadway work, improvements will be made at the intersection of Branch Hill-Guinea Pike and Cook Road/Weber Road, including upgraded traffic signals and designated turn lanes.
Project Will Be Completed in Three Phases
Phase 1 is expected to last approximately five weeks, from June 4 through July 9:
  • During Phase 1, work will take place on the northern end of Branch Hill-Guinea Pike and Cook Road.
  • A detour will be put in place for through traffic.
  • Access within the project area will be maintained for local property owners only. 
  • Permissible traffic movements during this phase will be: 
    • Right turn only from Branch Hill-Guinea Pike to Weber Road
    • Left turn only from Weber Road to Branch Hill-Guinea Pike 
Phase 2 is expected to last approximately five weeks, from July 9 through Aug. 15: 
  • During Phase 2, work will take place on the southern end of Branch Hill-Guinea Pike and Weber Road. 
  • A detour will be put into place for through traffic.
  • Access within the project area will be maintained for local property owners only.
  • Permissible traffic movements during this phase will be: 
    • Right turn only from Branch Hill-Guinea Pike to Cook Road
    • Left turn only from Cook Road to Branch Hill-Guinea Pike
The final phase of work will take place from Aug. 15 through the fall but will not result in full-time road closures. All roads will be reopened to through traffic with only minor temporary closures taking place as crews complete the final components of the project.  

The Branch Hill-Guinea Pike widening project is being completed in partnership with Miami Township and Milford Schools to improve access to Boyd E. Smith Elementary School and support safer travel along Branch Hill-Guinea Pike. A center turn lane will support smoother travel and help to reduce potential accidents by separating turning traffic from through traffic. The addition of a new sidewalk will provide safer pedestrian access in the area, and drainage improvements will enhance stormwater management along the road and in the surrounding subdivisions.  

More information about the project can be found on our website