The Contractor will be removing driveways the week of April 16
th on 63
rd Street between Sunset Terrace and Colby Avenue. They will also begin pouring driveways and sidewalk once grading is complete. Restoration will begin on the segment where concrete has been placed.
The weather the coming week will determine how much gets completed.
Residents will need to remove all vehicles out of their driveways and garages by 7:00 a.m. when work starts on their segment. They will be working one segment/block at a time. They anticipate it will take approximately 1-2 weeks per block/segment
.
Notices will be given prior to driveway removal for those residents south of Sunset Terrace. Residents on 63rd Street will have received a construction newsletter on the project. Lane closures on 63
rd
Street will occur during the
construction of the sidewalk. You can expect lane closures during the times of 9 a.m. and 3 p.m. on 63
rd
Street
.
For weekly updates, please visit http://www.windsorheights.org/205/Sidewalk-Improvement-Project.
|