PROGRESS REPORT
At Cheyenne,
work is nearly complete on the new additions. Crews are putting the final paint on the exterior of the gym, after discussing colors with nearby neighbors and HOAs. Inside the gym, flooring has been installed and finishing touches are in the works. The entire project is wrapping up on time, and Roadrunner 8th graders can look forward to graduating in the new gymnasium.
At Hopi, framing of the classroom building is now complete, and exterior wall installations are underway. Crews have begun framework for the new administrative building, which will also house additional classroom space.
At Pima,
classroom building framing is still underway and the center slab has been poured. The school's new circular drive is also starting to take shape, as you can see in the photo below.
*From the March 9 newsletter:
On Tuesday, February 27, the SUSD Governing Board voted to suspend the Hohokam rebuild as well as the Central Kitchen project. The Board also voted to pursue legal action to terminate the contracts for both projects. Work had
not yet begun at
Hohokam
. Any preliminary design proposals have been removed from the SUSD website to avoid confusion.
|