The intersection of 10th Avenue and Chandler Street, as well as the entrance to Jefferson High School, will reopen tomorrow (Friday).

Water main has been installed to 18th Street, and concrete pavement repairs and paving work has been following behind the water main work.  

Next week, water main will be connected to existing water main on 18th Street, which completes water main installation on this project. Services on Chandler Street and 18th Street are being transferred and this work will continue next week. Remaining work on the new access to the Jefferson High School softball complex will also be completed. 

Late in the following week and weeks ahead, existing asphalt on Chandler Street will be removed and the new asphalt surface placed, with final grading and sodding to complete the work.

As always, if you have questions and concerns about this project, please do not hesitate to contact a member of our project team.