PAVING FOR PROGRESS
O Avenue NW       

Construction Update: 11-6-18
Work continues to move forward on O Ave. The goal is to be substantially complete by the Thanksgiving holiday; we hope Mother Nature continues to cooperate and grants favorable construction weather. 

Over the next few weeks, as weather allows, crews will continue to install new sidewalks and driveways.  

Some additional water main work needs to be performed between 10th St and 11th St, so please be on the lookout for temporary water service interruption notices.

As always, thank you for your patience! 



Contractor 
Boomerang Corporations (Formerly named Ricklefs) 
Cory Elwick
Cell: (319) 480-8184

City Construction Inspectors
Ben Matt
319-521-5711

Eric Bahl
319-286-5531