PAVING FOR PROGRESS
Oakland Road   NE   


Construction Update: 11-15-18
 
With the colder weather, construction work has slowed a bit, but crews will continue to move forward.  The contractor still plans to pour pavement on 31st St, as well as more driveways. If weather still allows, crews will continue working on curb and gutter, and sidewalk/retaining walls.  Some of this work will result in periodic lane closures that will shift traffic over, but one lane of traffic each direction will remain open.

Thank you for your patience as we continue to complete improvements!