Construction Update: 8-28-18

 

Thank you to everyone's patience as we transition to the start of the new school year. The intersection of Wiley Blvd and Johnson Avenue has been operating smoothing, and we thank everyone for their patience. 

As a reminder, you can download material on roundabouts, see photos, and watch videos on the City's website: www.cityofcr.com/roundabouts 

An update on the Johnson Avenue project: Starting on Wednesday, August 29, the contractor will continue working on Johnson Ave east of Wiley Blvd up to the intersection of Johnson Ave and Wellesley Ct.  The current detour will remain in place.

When the weather permits, contractors will continue working on sidewalk and sod placement between Jacolyn Dr and Wiley Blvd.

As always, thank you for your patience!

Contractor 
Boomerang Corporation (Formerly named Ricklefs) 
Cory Elwick
Cell: (319) 480-8184

City Construction Inspectors
Jeremy Blok
(319) 775-3386

Eric Bahl
(319) 286-5531

RESOURCES

Pictures, videos, and other material on roundabouts is available on  the City's  website:

VIDEO: Introduction to roundabouts 

How roundabouts work