Traffic was shifted to the south side of Jenkins Road between 158th Avenue and Murray Boulevard in early April. The contractor now is focusing their effort on the remaining portion of the new bridge, storm pipe and structures, utility upgrades, and the retaining wall along the north side. 

The contractor has completed the construction of the new bridge’s west abutment and associated retaining wall on both sides of the new bridge. The contractor is focusing on the construction of the east abutment at the north end of SW 153rd Avenue.