Thank you for signing up for weekly updates on bond & override projects within SUSD. We are committed to transparency through this process, and we welcome your feedback. Like you, we can't wait to see our new schools go up and our existing schools improve.

NEW FIELD FOR THE FIREBIRDS!
Join Us for a Celebration!

Tonight, we will officially cut the ribbon on the new football field at Chaparral, the third field completed under the 2016 bond override.  



We hope to see you there!

WEEKLY PROGRESS

On Tuesday, September 12, the Governing Board got an update on bond and capital override expenses, to date. There are three summary documents showing budgets and expenditures:
Also this week,  architects provided color-coded floor plans for the new Hopi buildings, to better show what space will be used for what purpose. 
All of these documents can be found online at  bond.susd.org .