PAVING FOR PROGRESS
29th Street Drive SE       


Construction Update: 4-13-17
 

Work is moving forward on 29th St Dr. Crews are currently working on pavement improvements (milling and overlay), curb and gutter work, and are continuing the sidewalk and driveway replacements and improvements. This activity will continue during the next few weeks. 

Driveways and sidewalks will be temporarily blocked or closed as crews work on the paving. Whenever possible, they will work to minimize the amount of time that driveways need to be closed. 

As a reminder, starting on Monday, April 17, the westbound lane will be closed and traffic will transition to a one-way, eastbound only pattern. This will allow crews to work more efficiently at the pavement removals and repairs. 

Thank you again for your patience and understanding as we work on this project! 

Contractor 
Ricklefs Excavating LTD
Cory Elwick
319-480-8184

City Construction Inspector
Jason Junk
319-286-5724