Scottsdale Unified School District | Bond Update 11/17/17

Thank you for signing up for weekly updates on bond & capital override projects within SUSD. We are committed to transparency throughout this process, and we welcome your feedback. Like you, we can't wait to see our new schools go up and our existing schools improve.

YOU'RE INVITED!
GROUNDBREAKING CEREMONY
 
Pima Traditional School 
(formerly Pima Elementary)
8330 E. Osborn Rd.
Scottsdale, AZ 85251

Friday, December 1
9:00 a.m. - Flag Ceremony
9:15 a.m. - Groundbreaking

The community is welcome to join us as we celebrate the start of a new chapter. We're  Leaving a Legacy, Starting a Tradition.


WEEKLY PROGRESS

On Tuesday, November 14, the Governing Board voted to approve the start of construction at  Pima. The vote clears the way for fences to go up and ground level work to begin in December. Vertical construction is expected to follow in January. Please join us for the celebration above.

Also this week,  architects shared the new exterior renderings for Hopi, based on input from the community. Earlier this month, more than a dozen teachers met with the Hopi Rebuild Committee to vote on the new design, and they chose a Mid Century Modern Style. This design shift is in addition to changes already made to the interior of the building, based on community feedback. For more photos, visit bond.susd.org


Finally this week, the track surrounding the new Coronado football field is taking shape. We hope to reopen the field after the Thanksgiving holiday. Thank you for your patience while this work is underway.


Track surfacing at Saguaro and Chaparral begins December 12.
RUMOR OF THE WEEK ( or: Myth Busting)

A two-week streak with no rumors! Let's keep the information flowing. Have a great weekend.
Click here to learn more