MiTechnology is designed for greater technical visibility - to offer you the latest and most relevant of MiTek's technical information and specifications. For builders, design professionals, suppliers, building inspectors: this bulletin will keep you current and give you quick access to additional information and support documents. It will also link you to the full range of resources we offer you on our website, or through our customer support team.
VTT Valley Truss Tie

The VTT is a Valley Truss Tie designed to transfer loads from a valley truss into the supporting structure below. It also resists the sliding forces from downward loads when the valley truss is set upon a sloped lower roof. The ability to resist the sliding force eliminates the need for support wedges under the valley truss bottom chord or special order valley roof trusses with a bevel-cut bottom chord.

Materials: 18 gauge
Finish: G90 galvanizing
Patents: Pending


FEATURES

* Double-dimple nail holes assure the nails are driven in at the correct  angle into the supporting member every time.

Flat design requires no field bending to match the supporting roof pitch.

* 2-Ply steel with stiffening ribs provides a high resistance to sliding forces
from downward loads.

* Prong teeth help hold the VTT in place while nailing.

* Accommodates supporting roof pitches from 0/12 to 12/12.

* Pitch guide embossments allow attachment to valley truss on ground.

Installation:
  • Mark the location of the supporting truss located below the lower roof sheathing.
  • Place the VTT flat against the valley truss, centered over the top chord of the truss below. Tap the top edge down with a hammer to engage the prong teeth.
  • Nail the VTT to the bottom chord of the valley truss using (3) 10d x 1-1/2" nails.
  • Install (3) 10d common nails through the double-dimples and drive them through the sheathing into the top chord of the supporting truss below. One nail will be centered in the top chord below. The other two nails are driven in at preset angles guided by the dimple holes.
Alternate Installation for Ground/Pre-Placement of VTT
  • Mark the location of the supporting truss located below the lower roof sheathing. Center VTT horizontally on that mark.
  • Use pitch guide embossments on part to locate the vertical position of VTT. Pitch numbers on connector are the numerator in the pitch slope ratio. (i.e. "6" indicates a 6/12 pitch, "12" indicates a 12/12 pitch, etc.)
  • Secure the VTT to valley truss with (3) 10d x 1-1/2" nails.
  • When valley truss is hoisted into proper position on roof, install (3) 10d common nails through the double-dimples and drive them through the sheathing into the top chord of the supporting truss below. One nail will be centered in the top chord below. The other two nails are driven in at a preset angles guided by the dimple holes.
1) Uplift Loads have been increased 60% for wind or seismic loads; no further increase shall be permitted.
2) Uplift loads are based on installation over 7/16" or 15/32" sheathing.
3) Downloads have been increased for snow, construction and wind loads; no further increase shall be permitted.
4) NAILS: 10d x 1-1/2" nails are 0.148" dia. x 1-1/2" long,10d nails are 0.148" dia.  x 3" long.
For more information about the VTT Valley Truss Tie  