Airfield Construction
The rain has temporarily subsided in the Central Texas region and construction crews are making substantial progress on the runway reconstruction.
The upcoming weeks will focus on finishing electrical work. Paving is expected to begin on Tuesday, August 4.
We'll be sending out a special email regarding the next phase of construction as soon as we have the dates firmed up.
Please continue to check
NOTAMs.
Entrance Construction
Crews will be paving the widened section of the entrance tomorrow, July 22. This work should not disrupt the flow of traffic, but please use caution when navigating the area.
On Friday, July 24, the remaining width of the entrance will be paved. Starting at 7:00pm, the entrance will be narrowed to one lane. Crews will be on site directing traffic and work should be completed by 3:00am on Saturday morning.
The final lift of asphalt will not be laid until the end of the project to avoid damage from construction equipment.
|