Pool area and landscaping
 
May 3, 2017
The final pieces of the Wilson High School Phase II Modernization and Addition are coming together. Current projects include installation of an all-weather track and field, construction of a new music building, and a variety of minor campus site improvements. A grand opening celebration next fall (date TBD) will give families, alumni and the community a chance to tour these new amenities as well as the new academic building and gym and pool upgrades.

For questions or more information, email Planning and Construction.
TRACK AND FIELD UPDATE

Athletic field turf installation is in progress.

Track and field work should be complete in June.

 

Asphalt and concrete flatwork installation at the shot put area.

 

 

MUSIC BUILDING UPDATE

Acoustical panel installation in progress. This is part of the band/orchestra room's cloud ceiling in the new music building. The new building should be complete in July.
 
Questions?

Please send questions about the Wilson High School construction project to
Alicia Lawver, Communication Coordinator, at  [email protected].