22 MAJOR PROJECTS FOR THIS SUMMER
As I mentioned at the opening of this newsletter, there are 22 major projects. Here's a quick summary of the major road construction projects planned this summer. You'll also find links below to access updates on these projects.
CITY OF NAMPA
(1) 11th Avenue N/Industrial Road Reconstruction
(2) 12th Avenue Access Control (Lake Lowell to 7th St S)
(3) FY17 Chip Seal Projects - See planned chip seal projects in a map down below.
(4) Idaho Center Blvd (Cherry Lane to CWI) Reconstruction
(6) Nampa High School Pedestrian Improvements
(7) Midland & Karcher Bypass Intersection Modifications
(8) Roosevelt Avenue/1st Street South Water Upgrades
(9, 10) 12th Avenue (SH45) HAWK Crossing (11th Street South & Sherman)
(11) South Nampa Bike/Pedestrian Improvements
(12) Southside Blvd Pressure Reducing Valve & Pressurized Irrigation Line
(13) University District Chip Seal & Bike/Pedestrian improvements
(14) Western Regional Lift Station Pressure Sewer, Phase II
|
|
|
This is I-84 between Nampa and Caldwell before temporary patches were applied earlier this year. The road will be rebuilt this summer. The schedule has not been set at this time.
|
IDAHO TRANSPORTATION DEPARTMENT
Click
here to view the ITD website for these projects
- make sure to click on "Construction Projects" tab, then expand the Canyon County section
(5) Karcher (SH55) and Midway Intersection Improvements - Tentative
(15, 16) I-84 Reconstruction (Franklin Boulevard to Franklin Road)
(17) I-84B Rebuild (from Northside Boulevard to Grant Street)
(18) Karcher Road (SH55) & Lake intersection
(19) SH45 micro surfacing
(20) SH55 pavement rehab (Middleton Road to Pride Lane)
(21) US20/26 resurfacing (Locust Grove to Borchers Lane)
NAMPA HIGHWAY DISTRICT
Click
here to visit the Nampa Highway District website.
(22) Cherry Road rebuild