ORACLE 
BUILDING 09  \\   31,000 sq. ft.  
BUILDING 10  \\   120,000 sq. ft.

SC Builders filled the last spaces on Oracle's Santa Clara campus with two out-of-the-ground buildings over a 15 month period.  Both structures were designed to blend in with the rest of the campus by including a mix of curtainwall, brick, EIFS facades, and a matching standing seam metal roof. 

Building 09 is a fully functional testing space designed around the tools and equipment that were relocated from existing testing facilities.  To support these tools, our team installed a new deionized water skid, CDA system, LN2, STARLINE power, and a 10 Meter anechoic chamber.

Building 10 is a three-story 120,000 sq. ft. building built to house over 550 occupants and boasts a server lab, Cloud Café, and classroom space, along with other necessary office amenities.

In addition to the incredible support from Oracle's in-house management team, we were lucky to work with RMW Architecture & Interiors, and also had the incredible support of Compass Solutions.

"Having a successful project truly takes a collaborative effort.  As the project architect, I had the pleasure of working with an SC Builders team whose leadership, proactive approach, attention to detail, and great teamwork was instrumental in the success of the project."

Patrick Todd
Project Manager
RMW Architecture & Interiors

Photographs by Jasper Sanidad
   Announcing SC Builders' recent promotions...

  ...congrats team!