Repaving 174th Avenue
Ottawa County Road Commission will be repaving 174th Avenue from Van Wagoner to Wilson. This will involve an asphalt overlay. Road milling has already taken place. The first layer of asphalt will be placed on Tuesday, August 8. Traffic will be limited to one lane. Manhole work will be done on August 8 and Thursday, August 10, which will require short sections of flagging. The second layer of asphalt will be placed on Monday, August 14 and Tuesday, August 15. Traffic will again be limited to one lane. Shoulder work and striping will take place on August 14, 15 and 16 and will result in limited traffic interruptions.
This schedule is subject to revision, and is weather-dependent.
|