Spring Lake Fire Station
There has been much progress on the new fire station. The metal roof is being installed, windows are being installed, and the final concrete is being poured. Inside the building, wallboard has been installed and much of it has been primed and had a first coat of paint added. Interior tile work is also almost completed.
The expected completion date is October 15, 2016. There will be a ribbon cutting and public open house after that date. Our 2016 Fire Prevention Week activities will be at the old station on 148th Avenue for one more year.
This new Fire Station Building Project is on time and on budget, and will serve us all for the next 50 years.
|