City of Birmingham, MI
W. Maple Road  Paving  Project Update: 9-2-16
Project is 60% Completed
The following is a brief update for the W. Maple Road Paving Project:  
  • Concrete removal and patching in the roadway is now 95% complete.  
  • The first (out of two) courses of asphalt has been installed on the west end of the job from Cranbrook Rd. to Chesterfield Ave.
  • The contractor anticipates moving forward on the remaining easterly segment of the job about the middle of next week.
  • The project is now about 60% complete, and is targeted to open in the middle of September. 
For more information, contact the Engineering Department at 248-530-1840.
   