City of Birmingham, MI
W. Maple Road  Paving  Project Notice: 9-7-16
Asphalt Paving Scheduled for Thursday, Sept. 8
ATTENTION RESIDENTS - W. MAPLE  PAVING PROJECT NOTICE:
 
ASPHALT PAVING SCHEDULED
THURSDAY SEPTEMBER 8, 2016
 
On Thursday, September 8th, the Paving Contractor will be installing the first course of asphalt on W. Maple Road (between Chesterfield and Southfield).  The Contractor is expected to arrive for this work at about 7:00 AM, and proceed to pave the road, starting with the south side/lane, then the middle and finally the north side/lane.  The work is expected to be completed in two (2) days.
 
If you will need access to a vehicle either September 8th or 9th, and your driveway accesses the section of road listed above, we ask that you park on an adjoining street.  The Police Department will be notified to not ticket cars parked on adjacent streets in residential permit parking areas. Homes on the south side of W. Maple Road need to have their vehicles moved by 7:00 AM and homes on the north side by NOON on the scheduled paving days (9/8 and 9/9). Once the asphalt has been placed, and cools, the road will be reopened to LOCAL TRAFFIC ONLY traffic later in the day. 
 
We will need your cooperation to ensure a successful job. Before the new pavement is placed, the road will be swept, and a tack coat will be placed. Once the tack course is placed, it is very important to not drive on the road, since the tack coat can stick to cars and driveways and is very difficult to remove.  
 
The top layer of asphalt is scheduled to be placed starting on Monday, September 12th and is expected to take three (3) days to complete. If you will need access to a vehicle on those days, and your driveway accesses the section of road listed above, we ask that you park on an adjoining street during that time. The Police Department will be notified to not ticket cars parked on adjacent streets in residential permit parking areas.  Shortly after the asphalt has been placed and given time to cool, that section of the road will be reopened to LOCAL TRAFFIC ONLY.  For this portion of the project, vehicles should be moved by 7:00 AM as access cannot be guaranteed after the paving operation has begun.
 
Although not anticipated, in the event of rain, the project may have to be postponed until a later date, and you will be notified again. We will most likely not know of a postponement until after the day has begun.
 
We understand that the above restrictions will cause inconveniences. We hope that you will be willing to work with us as we attempt to bring this portion of the project to a close. If you have any questions, feel free to ask the City of Birmingham representative on site.  Or, you may call the Engineering Department at 248-530-1850.

   