The following is a brief update for the Villa project:
- The Contractor has completed paving the north side of Villa Ave. with the exception of the Yankee St. intersection;
- Next week, work will begin on the south side of Villa Ave.;
- The Project is approximately 65% complete
- See attached photo(s).
If you have any questions or need additional information, please feel free to contact the Engineering Department at (248) 530-1850.