W. Maple Road  Paving  Project Update: 8-16-16
Project is 45% Completed
The following is a brief update for the W. Maple Road Paving Project:
  • The Contractor is currently finishing up the joint repairs on W. Maple Road.  This work will be followed by pavement repairs in preparation for the paving portion of the project;
  • The Contractor anticipates installing the base course of asphalt sometime next week (August 22-26, 2016);
  • The project is approximately 45% completed with a finish date targeted for Sept. 2, the Friday before Labor Day.
  • See attached photos showing repair work underway.
For more information, contact the Engineering Department at 248-530-1840.
 