The following is a brief update for the W. Maple Road Paving Project:
- The Contractor is currently finishing up the joint repairs on W. Maple Road. This work will be followed by pavement repairs in preparation for the paving portion of the project;
- The Contractor anticipates installing the base course of asphalt sometime next week (August 22-26, 2016);
- The project is approximately 45% completed with a finish date targeted for Sept. 2, the Friday before Labor Day.
- See attached photos showing repair work underway.
For more information, contact the Engineering Department at 248-530-1840.