City of Birmingham, MI
 Additional foundation work needed for W. Maple Rd. Project; Completion date changed to Sept. 12
Progress continues on the resurfacing of W. Maple Rd. from Cranbrook Rd. to Southfield Rd. 
 
The goal of this project was to remove the asphalt overlay placed in the 1990's, make spot repairs to broken slabs and damaged joints, and then installing a new asphalt overlay with the intent of having a 20-year design life. The majority of the  underlying concrete pavement on Maple Rd. dates back to the 1950's or earlier.  Much of this concrete is still in good condition, and can continue to perform well into the future.  
However, once the asphalt overlay was removed, the amount of damaged concrete exceeded our expectations by about 25%. The patching process takes time, as crews tear out and haul away old concrete sections. It has now been confirmed that large sections of the street were originally built on clay, rather than crushed limestone, as is done today. These base issues are being addressed now as well to make sure that the new road will last for many years to come.

The contractor has been putting in long days recently to meet the extra work load.  Even so, the additional work necessary to repair the road foundation will add an additional week onto the project. As a result, the new opening date for West Maple Road is now planned for  Monday, September 12. We apologize for the delay, and ask for the patience of the community as we move closer to a new, improved driving surface on Maple Rd.  
Also, please be aware that the contractor will be working again  this Saturday  and  Sunday .  Work  on Sunday  will not start until  9 a.m .  

If you have any questions or need additional information, please feel free to contact  the Engineering Department at 248-530-1840.
 

Like us on Facebook          Follow us on Twitter