City of Birmingham, MI
Villa Avenue Paving Project Notice 9.1.16:
75% Completed
The following is a brief update for the Villa Ave. Paving Project:
  • The Contractor has completed paving the south side of Villa Ave;
  • Work has begun on the driveway approaches on the north side and will continue next week; 
  • Once the driveway approaches and sidewalks are completed, the area between the curb and sidewalk will be rough graded. At that point, there will be approximately a two (2) week window for the residents to have any damaged sprinklers repaired prior to topsoil and sod being installed.  Residents will be notified at that time;
  • The Project is approximately 75% complete;
  • See attached photos which show the current progress of the project.
 
 
If you have any questions or need additional information, please feel free to contact the Engineering Department at (248) 530-1850.

 

 

 

 
Like us on Facebook          Follow us on Twitter