City of Birmingham, MI
West Maple Road Asphalt Resurfacing
Project Update 7.25.16
The following is a brief update for the W. Maple Road Resurfacing Project:
  • Sidewalk, ramps and curb excavation and removals on south side of W. Maple Road have been completed;
  • This week concrete will be poured on the south side of W. Maple Road for sidewalk, ramps and curbing;
  • Also, this week excavation and removals for sidewalk, ramps and curbing on the north side of W. Maple Road will begin;
  • W. Maple Road is scheduled to be closed to through traffic beginning Wednesday, August 3rd for approximately four (4) weeks;
  • See attached photo(s).


 

For questions during the project, a City of Birmingham representative will be on site and available to help answer questions. For more information, you may also contact the Engineering Department at 248-530-1850.