The following is a brief update for the W. Maple Road Resurfacing Project:
- The Contractor is continuing to pour sidewalks, ramps and curbs on the south side of W. Maple Road;
- This week sections of sidewalk, ramps and curbing will be removed on the north side of W. Maple Road
- Milling of W. Maple Road will begin later this week;
- W. Maple Road will be closed to through traffic beginning Wednesday, August 3rd for approximately four (4) weeks. The detour map is below;
- See photos of the project below.
For questions during the project, a City of Birmingham representative will be on site and available to help answer questions. For more information, you may also contact the Engineering Department at 248-530-1840.