The following is a brief update for the Villa Ave. project:
  • The Contractor has completed installing all sanitary sewer leads and water services;
  • The new storm sewer on the south side of Villa Ave has been completed;
  • This week the Contractor will finish installing the new storm sewer on the north side of Villa Ave;
  • Later this week it is expected that the Contractor will begin excavating the road and preparing the base;
  • See photos of the project below.
If you have any questions or need additional information, please  call the Engineering Department at 248-530-1840.


 