The latest news on the Miller Avenue Streetscape Project.
Miller Avenue Streetscape Project Update Week of November 20 - 24, 2017

What happened last week:
Work crews:
  • Placed landscaping in the Mainstreet area.
  • Installed two tide gates in the Marsh area.
What is happening this week:
Work crews are:
  • Placing landscaping in the Mainstreet area.
  • Placing the seating and decking at the Reed Creek Overlook, and installing concrete.
  • Conducting final work at the two tide gates in the Marsh area.
What to expect in the next few weeks:
Work crews will:
  • Install final project landscaping.  
  • Conduct second phase of night work to line the sewer system under Miller Avenue. Work is scheduled to begin on Monday, November 27, 2017. Please see the article below for details.
  • Final clean up items as part of the close out of the construction project.
Please Note: There may be parking restrictions and lane shifts to allow for the work mentioned above and other miscellaneous items. Rain and other factors may impact the schedule, therefore, all dates are subject to change.
Reed Creek Overlook nearing completion.
Sewer Lining - Day and Night Work Scheduled

As a part of the Miller Avenue Streetscape Project, the City's contractors will repair the public sewer pipes along Miller Avenue using a construction method call "cured-in-place pipe" (CIPP), which involves installing a flexible tube that gradually hardens to form a rigid, smooth surface that seals cracks and restores the sewer pipe lining.

Existing manholes are utilized for the majority of construction, minimizing the amount of open trench excavation required for the job.Construction will take place during the day and at night.
The hours are 7 pm to 7 am, with equipment and traffic control measures into mid-morning as needed.

Night work is necessary because the lining must be placed when sewer flows are reduced, as was approved as part of the construction contract. Anticipated impacts for the work are lane closures, parking restrictions, construction noise, and the odor from the lining process. Notices will be delivered to those residences or businesses directly impacted by the work in terms of sewer access.

The tentative work schedule is as follows:

Date Location
Monday, November 27 324, 340 and 360 Miller Avenue
Tuesday, November 28 Montford and Miller Avenue intersection
Wednesday, November 29 Evergreen and Miller Avenue intersection

Residents, motorists, and businesses may smell a chemical odor during the pipe-lining work.

The odor is from the chemical styrene, which is in the resin liner installed inside the pipe. Styrene is a clear, colorless liquid that is used in the production of many everyday products such as plastic packaging, counter tops, disposable cups and containers, insulation and others. We are constantly exposed to small amounts of styrene in both ambient and indoor air, mostly attributable to emissions from building materials, and consumer products.

Learn more:

Watch the video on how CIPP works.
Download an information sheet about Styrene
Hundreds Turn Out for MillerFest - a Community Celebration of the New Miller Ave

On Saturday, November 4th, hundreds of Mill Valley residents joined their neighbors, local merchants and City officials to celebrate the new Miller Avenue with a ribbon cutting ceremony, live performances, walking and bike tours, music and lots of fun for the whole family.

"We should all feel very proud of this accomplishment," Mayor Jessica Sloan said. "This achievement is the result of the entire community working together to create something beautiful," she said.

Thanks to everyone who participated and made this a great event!

Thank You for your Patience During Construction

The City of Mill Valley would like to send out a special thank you to the Mill Valley community for your continued patience during construction and to the M&G construction crew for its continued progress on the Miller Avenue Streetscape Project!  
Contact Us:

Construction Specific Questions or Concerns:  
Please contact 4LEAF Construction Management 
Phone: (415) 328-6972 
Email:  [email protected]

General Questions or Concerns:
Please contact Linn Walsh, Assistant to the City Manager  
City of Mill Valley 
Stay Informed
                      City of                                                 Mill Valley
                      Mill Valley                                            Chamber of Commerce  
                       www.cityofmillvalley.org                         www.millvalley.org