The Warren County Transportation Improvement District (WCTID), along with the Ohio Department of Transportation (ODOT), the City of Mason, Deerfield Township, and other local partners, are working on making transportation improvements throughout southwest Warren County to ensure our local infrastructure meets the needs of our growing community.
 
Currently, there are four active projects under construction - Socialville-Fosters Road Improvements, the  relocation of Columbia Road,   Kings Island Drive Improvements and the Irwin-Simpson Road Widening project. Each week, we will provide an update on the status of these projects.
 
While we recognize there is a significant amount of roadwork taking place this summer, each project has been carefully planned and organized as part of a coordinated regional program - including the Interchange Improvements at the Fields-Ertel & Mason-Montgomery Road exit - that will increase mobility, improve safety and expand access to a growing number of businesses and world-class recreational destinations in our area.
 
Please visit our partners at ImagineWesternRow.com for more detailed project information and a more thorough discussion of our regional improvement program.
 
Thank you for your patience during construction season, and as always, please slow down and drive safely. 



CHECK THIS OFF THE LIST
To date, crews have completed the following:
  • The recent nighttime pile driving has ended and all pile driving work has been concluded.
  • Utility work at the intersection of Socialville-Fosters Road and Innovation Way has been completed.
UP NEXT
This week, crews will focus on the following:
  • Work on the bridge over I-71 continues as crews make progress on construction of the piers.
  • Concrete curb is being poured for the Roundabout at the intersection of Socialville-Fosters Road and Innovation Way.
KEEP AN EYE ON
Some issues to be mindful of as work continues:
  • Additional nighttime work is ongoing, but the noise level should not be as intense as the recent pile driving work.
  • Various lane closures on I-71 at the Socialville-Fosters bridge will continue to occur nightly between 7 p.m. and 7 a.m.
  • The six week closure at Socialville-Fosters Road and Innovation Way continues through early July.
  • The 40-week closure on Socialville-Fosters Road at the bridge over I-71 continues through the end of the year, and the detour (Mason-Montgomery Road to Western Row Road to Columbia Road) remains in place during that time.


CHECK THIS OFF THE LIST
To date, crews have completed the following:
  • Clearing of trees at the southeast corner of Western Row Road and Columbia Road has been completed.
  • Dirt from neighboring construction sites is being transported to this project area for reuse.  
UP NEXT
This week, crews will focus on the following:
  • Utility work, including gas, electric, storm and phone systems are all being relocated.
KEEP AN EYE ON
Some issues to be mindful of as work continues:
  • There are no closures in place related to this work; however, you may notice flaggers in place helping with traffic while heavy equipment is moved in and out of the area. 


CHECK THIS OFF THE LIST
To date, crews have completed the following:
  • Work on the inside lanes of Kings Island Drive from Soak City Drive to the new Kings Island entrance has been completed.
  • Curbs are being installed along the west side of the road.
  • Curbs for the median islands have been completed and light poles have been installed. 
UP NEXT
This week, crews will focus on the following:
  • Construction is now taking place on the outside southbound lanes on Kings Island Drive as crews work on the southbound lanes and the installation of the new bike path.
  • Electric work is now taking place on the improved lighting along the new roadway.
KEEP AN EYE ON
Some issues to be mindful of as work continues:
  • There are no full closures or detours in place related to this work; however, there are various lane closures and traffic impacts throughout the project area, primarily from Soak City Drive to the new entrance of Kings Island. If it's been a while since you've driven this road, the traffic pattern has likely changed, so please slow down, read the signs, and be mindful of other drivers as you drive through this area.
 

CHECK THIS OFF THE LIST
To date, crews have completed the following:
  • All sewer work and water main relocation work has been completed. However, access to connect to the new system will not happen until 2017.
  • Initial paving work west of Auburn Road has been completed.
UP NEXT
This week, crews will focus on the following:
  • Crews are working on sidewalk placement west of Auburn Drive, pouring driveway approaches in that same section, and moving quite a bit of dirt to accommodate construction.
KEEP AN EYE ON 
Some issues to be mindful of as work continues:
  • Irwin-Simpson Road between Charleston Park and Butler-Warren Road is currently closed to through traffic, but local traffic and residents will have access to the area throughout construction. The road is expected to reopen in November of 2016.
  • The detour is Butler-Warren Road to Socialville-Fosters Road to Snider Road, and is marked with detour signage.