May 2016
Still Want More Info? 
Want to learn more about the work being done by the CCTID?

Come to our next board meeting on Friday, June 10, at 9 a.m., at the Clermont County Engineer's Office.

Tell Us What You Think!
Email: 
 
Phone:
513-835-2417
 
Like us on Facebook

Follow us on Twitter

Members Of The CCTID
Jeff Wright -
Chair of the CCTID and Miami Township Administrator
 
Ken Geis -
Vice-Chair of the CCTID and Union Township Administrator
 
Pat Manger, P.E., P.S. -
Secretary-Treasurer of the CCTID and Clermont County Engineer
 
Andy Kuchta -
CCTID Board Member and Director of the Clermont County Department of Community and Economic Development
 
Matthew Van Sant -
CCTID Board Member and President/CEO of the Clermont County Chamber of Commerce
 
John Becker -
Ex-Officio Member of the CCTID and State Representative, Ohio's 65th House District
 
Joseph Uecker -
Ex-Officio Member of the CCTID and State Senator, Ohio's 14th Senate District


Next section of work has begun on Branch Hill-Guinea Road 
Prior to resurfacing work that will occur on Branch Hill-Loveland Road from Branch Hill-Guinea Road to the Hamilton County line, project crews will be replacing two underground storm water drainage pipes.

TRAFFIC IMPACTS: Branch Hill-Loveland Road will be closed from Branch Hill-Guinea Road to Arrowhead Trail. A detour is now in place from Branch Hill-Guinea Road to Wards Corner Road to I-275 to Loveland-Madeira Road. 
 
Click the image above to view the detour from Branch Hill-Guinea Road to Wards Corner Road to I-275 to Loveland-Madeira Road

This work is part of the Branch Hill-Guinea Road Drainage Improvements Project, which consists of drainage improvements and widening along Branch Hill-Guinea Road between Branch Hill-Loveland and Branch Hill-Miamiville Road. Clermont County Engineer Pat Manger said that these coordinated series of repairs will significantly improve safety and travel through this area, particularly during this time of year when rainfall can often lead to problems on the roadway. 

"This improved drainage system will not only move water more efficiently from the roadway, but our improvement work will also eliminate the sharp drops and deep ditches along the roadside," said Manger. "In addition to the drainage improvements, the installation of paved shoulders will enhance safety for all traffic traveling through this portion of Branch Hill-Guinea Road."

Engineer Manger also provided the following update on two related - and now completed - projects:
 
1. WHAT: 
Work to replace a deteriorated section of water main between Branch Hill-Loveland and Branch
Hill-Miamiville Road. 
 
TIMING: 
Start date: Monday, March 21, 2016 
Expected completion: Tuesday, April 5, 2016
 
STATUS: 
 COMPLETED 
 
2. WHAT: 
Reconstruction and paving of Branch Hill-Guinea Road, which followed the completion of the above water main replacement work.
 
Improvements include 12' travel lanes and 2' shoulders, as well as curb and gutter work. (The previous lane width was 10' with little to no shoulder room and deep roadside ditches.)
 
TIMING:                                    
Start date: Wednesday, April 6, 2016
Expected completion: Tuesday, May 10, 2016
 
STATUS:
    COMPLETED


Visit GoClermont.org for more information.