Western Ave. water main project - weekly project report
Segment No. 1 and 2: N. Western Ave. 8" and 24" water mains - W. Diversey Ave. to N. Jones St. (East side). Complete.
Segment No. 3: W. Diversey Ave. 12" water main - N. Western Ave. to 120' N. of West Logan Blvd. (North side). Complete.
Segment No. 4: N. Western Ave. 8" water main - W. Diversey Ave. to N. Jones St. (West side). Concrete base course restoration is in progress.
Segment No. 5: N. Western Ave. 24" water main - W. Diversey Ave. to North Branch of Chicago River (East side). Water main and restoration complete (except for 4 future service transfer crossings near Wolfram and North of George).
Segment No. 6 N Western Ave. 12" water Main - West Branch of Chicago River to W. DIversey Ave. (West side) 12". Beginning of new water main construction tentatively scheduled to begin week of 2/23/15.
Segment No. 1: W. Nelson St. 8" water main - N. Western Ave. to N. Oakley Ave. Concrete base course restoration is 70% complete. Completion of concrete restoration to be scheduled weather permitting.
Segment No. 1: N. Western Ave. 8" water main - W. Belmont Ave. to W. Nelson St (East side). Concrete restoration complete, NB ramp scheduled to open to traffic (NB access to Belmont) on Friday 2/20/15.
Segment No. 1: N. Western Ave. 8" water main - W. Belmont Ave. to W. Nelson St (West side) Test holes and beginning of water main construction tentatively scheduled to begin week of 2/23/15.
Segment No. 2: N. Western Ave. 24" water main - W. Barry Ave. to W. Nelson St. (Center lanes) To be scheduled.
Segment 1: N. Western Ave. 24" water main - W. Addison St. to 300' S.S.L. of W. Roscoe St. (West side) To be scheduled.
Segment 2: N. Western Ave. 12" water main - W. Addison St. to W. Roscoe St (East side). Test holes complete. Beginning of water main construction tentatively scheduled to begin week of 2/23/15 at Roscoe
Scheduled work by others on Western Ave:
*** Contractor test-hole excavations will be scheduled to start at various locations within the Diversey / Western intersection for utility duct measurements, tie-up and support. ***
Contact information for water main crew:
Ray Holpuch - Resident Engineer - 312 907 5140
Water Department construction trailer is located at 2401 W. Fletcher