November 13, 2014
Project Updates
Penryn Overcrossing

The first night of the Penryn overcrossing lift was very productive. Despite the rain, the structure was lifted a total of 11" overnight. Seven more inches need to be lifted in order to achieve the federal clearance requirement.

 



Crews will continue the Penryn structure lift tonight, November 13.
I-80 will be closed again from 11 p.m. to 5 a.m.

The same detour route will be in effect.
Penryn Road, Horseshoe Bar, and Newcastle Road on/off-ramps will be closed during the lift process.
Detour information is available on Raise80.com/penryn

Interstate 80 is Open for Business During Construction
Caltrans welcomes businesses to advertise special offers on the Raise80 project website: www.RAISE80.com/open 

 

Let local residents and visitors know your business is open. Submit your "Open for Business Special" by downloading and filling-out the open for business form. Download the form!

 

Follow us on social media and we'll mention your business on our Facebook and Twitter newsfeeds.

 

Connect.
Promote.
Connect with the #Raise80 campaign on Facebook and Twitter! "Like" and "Follow" the #Raise80 for current construction information.

 

Following are links to the Facebook Page and Twitter accounts.

www.facebook.com/Raise80

www.twitter.com/Raise_80(@Raise_80)

Be Work Zone Alert
We remind drivers to slow their speed in the work zone. Workers are working within inches of live traffic. Traffic is unpredictable and sudden slowing or stopping may occur. Please do not peer into work zones as this can cause collisions if drivers are not paying attention to their driving. 

Questions?

Contact:

Deanna Shoopman

Caltrans District 3 Public Information Office

[email protected]530.632.0080


Caltrans District 3
c/o Deanna Shoopman
703 B Street
Marysville, CA 95901

STAY CONNECTED
Like us on FacebookFollow us on Twitter