September 24, 2014
Project Updates
Magra Overcrossing

The first night of the Raise80 project was a productive one. The first structure of the project, the Magra Overcrossing, was lifted a total of 7" overnight.
 





Crews will continue the Magra structure lift tonight, Wednesday, September 24, to lift the remaining 9". I-80 will be closed again from 10:30 p.m. to 5 a.m. The same 56-mile detour will be in effect.


Interstate 80 is Open for Business During Construction
Caltrans welcomes businesses to advertise special offers on the Raise80 project website: www.RAISE80.com/open 

 

Let local residents and visitors know your business is open. Submit your "Open for Business Special" by downloading and filling-out the open for business form. Download the form!

 

Follow us on social media and we'll mention your business on our Facebook and Twitter newsfeeds.

 

Connect.
Promote.
Connect with the #Raise80 campaign on Facebook and Twitter! "Like" and "Follow" the #Raise80 for current construction information.

 

Following are links to the Facebook Page and Twitter accounts.

www.facebook.com/Raise80

www.twitter.com/Raise_80(@Raise_80)

Be Work Zone Alert
We remind drivers to slow their speed in the work zone. Workers are working within inches of live traffic. Traffic is unpredictable and sudden slowing or stopping may occur. Please do not peer into work zones as this can cause collisions if drivers are not paying attention to their driving. 

Questions?

Contact:

Rochelle Jenkins 

Caltrans District 3 Public Information Office

[email protected] 

530.634.7670

Caltrans District 3
c/o Rochelle Jenkins
703 B Street
Marysville, CA 95901

STAY CONNECTED
Like us on FacebookFollow us on Twitter